Progress report

  • Work completed since 6 January
Since the 6th of January, we have completed all of our pre-production work including but not limited to the script and mise-en-scene document, we've got most of our props that'll be used in the film and we have confirmed with all the people we want in the film, when they need to be available for.
  • Any incomplete pre-production tasks
The storyboard and shot list for the production may need to be re-looked at in consideration of scenes/parts of scenes we may have added or modified over the past few days. Not only this, but the mise-en-scene document will have to display the fact that there has been a change in the actors playing lead characters for instance the most important one, being La Sombra's actor being replaced as a way of reflecting what his ethnicity is more likely to be - fair-skinned and of a reasonable height.

  • Next steps/action plan
Filming for the production should begin on 23/01/16 with the audio recordings having been done. For this to happen though we need to ensure that everyone we plan to have in the party scene of the 3-minute clip, will be available on the day that filming happens on and in addition to this we need to have all the props that we planned to utilise ready e.g. briefcase, syringe etc. 
  • Date filming will be complete
Seeing that things go to plan filming for the production should be complete on the first, if not second week of February.
  • Requirements for photo shoot next week
For the photo shoot next week, the main things that we require are appropriate clothing for the main character to truly deliver the aura that we want to with readers, all the props such as the syringe that will be used in the production to murder the supposed target and also that same actor that actually will be playing that mistaken target.